Solar Project Progress Tracking: How Is an EPC Progress Report Verified?

Construction

eyerod · · 9 min read

Aerial view of a solar construction site with post, table and module detection layers; a title card on verifying EPC-reported progress on site

Solar project progress tracking is the comparison of the work completed on site with the approved design, the planned quantities and the schedule. Drone data brings the number and location of visible components into this comparison. To verify physical progress, these measurements are assessed together with site checks, quality records and test results.

A weekly EPC report arrives. The first page gives the project’s completion percentage, followed by site photos. The questions an investor needs answered, however, are more detailed: How much work was done in which block? What changed this week? Where on site can the reported quantities be seen? Which items are behind the schedule?

A record that answers these questions lets the investor and the EPC team discuss progress on the basis of the same date, location and definition of work.

What does the progress percentage in an EPC report show?

Before assessing the progress percentage on a solar project, it is necessary to know what the calculation is based on. The quantity of installed modules, the time elapsed and the payments made express different things.

IndicatorQuestion it answers
Physical progressHow much of the defined work has been completed?
Status against the scheduleWhere does the work stand against the planned level on the report date?
Financial progressHow much of the budget or contract value has been spent or paid?
Quality and acceptance statusWhich checks and tests has the completed work passed?

Modules having been delivered to site, for example, does not show that they have been installed. Their being installed does not mean that the electrical connections and commissioning tests are complete either.

The progress percentage should preserve the difference between these stages. SolarPower Europe’s EPC guidelines also recommend defining activity-based calculation rules, weighting criteria and a reference schedule for tracking physical progress (SolarPower Europe EPC Guidelines).

How is solar construction progress verified?

Verification starts with setting up a structure in which it is possible to trace which data a reported quantity is based on. This requires the design, the site measurement and the reporting to use the same work items.

1. Setting the design and measurement scope

At the outset, the current design file, block boundaries, work items and planned quantities are brought together. The work breakdown structure (WBS) divides activities into trackable work packages. The bill of quantities (BOQ) defines these packages in units, meters, square meters or cubic meters.

What “complete” means should also be defined. For a table, erecting the mounting structure, placing the modules and completing the connection checks can be separate stages.

When the design revision changes, the basis of the comparison should be updated. Otherwise, correctly executed work on site can appear as a deviation because it is compared with an outdated drawing.

2. Collecting site data that matches the report date

The site measurement and the EPC report need to represent the same period. A difference between quantities from different dates may come from work carried out in between.

For drone flights, coverage, image resolution, overlap and positioning quality are assessed. The orthophoto produced from the processed images allows visible work to be reviewed on the same map as the design.

We covered this technical workflow in detail in how to track solar construction progress with drones.

3. Matching counts to locations

Visible components such as piles, posts, tables and modules can be detected and counted to the extent that image quality allows. The results are matched to the relevant block and design location.

Three states should be kept separate here:

  • Detected: The component could be identified in the image.
  • Not detected: No detection was produced for the component in the image; further review is needed.
  • Not assessable: Image quality, occlusion or a gap in coverage did not allow measurement.

A missing detection does not on its own prove that the work is absent. The match between the image and the design should be checked, and points that remain uncertain should be completed with a site record.

4. Reviewing differences against the EPC report

The comparison is made at block and work-item level. When a difference appears, the measurement date, design revision and completion definition are checked first. The count, site photo or related inspection record is then reviewed.

A general assessment such as “the report and the site do not match” thus becomes a question that can be examined: in which block, for which work item, and as of which date is there a difference?

How is the physical progress percentage of a solar project calculated?

For a work item tracked by unit count, quantity-based progress can be calculated as follows:

Progress rate = Quantity verified as having reached the defined stage ÷ Total planned quantity × 100

This rate represents only the named work item and stage.

The example below was prepared to illustrate the calculation; it does not come from a real project. The same design revision, report date and installation definition are assumed.

Block A module installationQuantity
Total modules in the design1,000
Planned to be installed by the report date700
Verified as having reached the installation stage600

In this case, the quantity-based progress of module installation is 60%, and the planned level for the same date is 70%. There is a gap of 100 modules, or 10 percentage points, between plan and actual.

This result describes module installation in Block A. On its own, it does not show the plant’s overall completion rate or a delay to the delivery date.

If a combined percentage is to be produced for the whole project, the weights of the work items should be set in advance. Pile counts, cable lengths and test completion cannot be added together directly. Items that cannot be measured should not be quietly left out of the calculation either; which records they are assessed with should be stated.

What does a planned vs. actual comparison reveal?

In solar progress verification, three comparisons answer different questions:

ComparisonQuestion it answers
Design vs. current siteWhich planned components can be seen, and in which location?
Schedule vs. current quantityWhere does the work stand against the quantity due by today?
Previous measurement vs. current measurementHow much changed between the two measurements?

New tables may have been installed in a block since the previous week. This shows an increase in quantity. Whether the work is progressing on schedule becomes clear only when it is compared with the quantity planned for the same period.

Likewise, no visible change between two flights does not prove that work has stopped. Cable connections, torque checks or other work that cannot be distinguished in the imagery may have been carried out in that period.

Which solar construction work can be measured with drone data?

The scope of aerial measurement depends on the component’s visibility, image quality, design data and the method used. The table below summarizes the general limits for RGB imagery and suitable photogrammetric outputs.

Work itemWhat drone data can provideWhat needs additional checks
Piles and postsCount and location of visible elementsEmbedment depth, pull-out test
Tables and mounting structuresVisible installation stage, count and layoutBolt torque, connection compliance
PV modulesCount and layout of visible modulesClamp tightness, electrical connection, microcracks
Roads and gradingVisible boundaries; elevation and volume change with suitable dataCompaction, layers and material quality
Open cable trenchesVisible route and lengthCable placement, checks before backfilling
Inverter and transformer stationsPresence and location of visible equipment on siteInternal connections, protection and commissioning tests

The work inside a backfilled trench cannot be verified from a surface image captured afterwards. Data collection should therefore be timed to the stage at which the work is visible.

Measurement precision involves a distinction too: GSD is not positional accuracy. GSD is the ground distance represented by one pixel. The reliability of the design-to-site match also depends on positioning, ground control and processing quality (Resolution and accuracy in photogrammetry).

How is drone data used in assessing progress payments?

Drone measurements provide supporting evidence for reviewing the quantity and location of reported work. In assessing a progress payment, these records are considered together with the measurement method and approval process defined in the contract.

A mounting structure appearing in an image, for example, can show the visible state of installation. If the related payment milestone depends on completed connection checks, the records of those checks are needed as well.

An ITP, or Inspection and Test Plan, defines which work is checked with which method and criteria. A punch list tracks open deficiencies and non-conformities with their locations, owners and closure evidence (punch lists and ITPs in solar projects).

Electrical safety and commissioning also require separate verification. IEC 62446-1 covers handover documentation, commissioning tests and inspection requirements for grid-connected PV systems. Aerial imagery does not show the results of these tests (IEC 62446-1 scope).

What should a progress report for investors contain?

For a report to be verifiable, it should be possible to get from a quantity in the summary table to the related site record. This requires the following information to be presented together:

  • Measurement date, report date and the design revision used.
  • Total, planned and actual quantities by block and work item.
  • Change since the previous measurement and the quantity gap against the schedule.
  • The location of findings on the map.
  • The source of the data: drone measurement, site check, test record or EPC statement.
  • Areas that could not be assessed and differences awaiting review.

When this structure is used across more than one solar project, portfolio reports also become more comparable. Different table types, project scopes and completion definitions should still be preserved, however. Two sites reaching the same percentage does not mean they have completed the same quantity or the same type of work.

eyerod Construction Intelligence brings together orthophotos, digital surface models and component counts produced from drone data with the records entered by the site team. These records help investors and EPC teams assess reported progress on the basis of shared site data.

Which work on a project can be tracked with drone data, and which additional records it needs, can be assessed with the eyerod team through the contact page.

Frequently asked questions

Can an investor track solar construction without visiting the site?

Visible work quantities and changes between periods can be tracked remotely with suitable drone data and design files. Quality checks, buried work and commissioning tests require site inspection and the related records.

Is drone data enough to verify an EPC progress report?

It contributes to checking visible quantities. Assessing the project’s overall progress also requires the schedule, completion rules, weights and evidence for work that cannot be measured from the air.

How often should drone flights take place for solar progress tracking?

Flight frequency should be set by the pace of construction and the reporting need. For work that is closed up quickly, such as trenches, relying only on the weekly report date can mean the necessary imagery is missed.

Does a drone measurement count as independent verification?

Independence depends less on the device used than on who collects, checks and assesses the data. The investor’s access to the data, the transparency of the methods and the verification responsibilities should be defined.